  1. PROJECT MILE STONE
S. No  Description Days % of Completion Completion Dates
1 Commencement Date-     07-July-2024(Provisional only)
2 Mile Stone-1 180 20 11-Feb-2025
3 Mile Stone-2 360 35 10-Aug-2025
4 Mile Stone-3 550 75 16-Feb-2026
5 Scheduled Completion date  730 100 15-August-2026
  1. PROJECT PROGRESS
    Physical Progress up to March 2025 = 7.10 %