- PROJECT MILE STONE
S. No | Description | Days | % of Completion | Completion Dates |
1 | Commencement Date- | 07-July-2024(Provisional only) | ||
2 | Mile Stone-1 | 180 | 20 | 11-Feb-2025 |
3 | Mile Stone-2 | 360 | 35 | 10-Aug-2025 |
4 | Mile Stone-3 | 550 | 75 | 16-Feb-2026 |
5 | Scheduled Completion date | 730 | 100 | 15-August-2026 |
- PROJECT PROGRESS
Physical Progress up to March 2025 = 7.10 %
-