Project Milestone Status
| S. No | Description | Days | % of Completion | Completion Dates |
| 1 | Commencement Date- | - | - | 19-March-2025 |
| 2 | Mile Stone-1 | 180 | 20 | 14-September-2025 |
| 3 | Mile Stone-2 | 360 | 35 | 13-March-2026 |
| 4 | Mile Stone-3 | 550 | 75 | 19-September-2026 |
| 5 | Scheduled Completion date | 730 | 100 | 18-March-2027 |