| Project Title |
: Construction of 4-Lane Access Controlled Greenfield Highway section of NH163G (Khammam –Vijayawada) from V. Venkatayapalem village at Design Ch. 220+480 Km to Brahmanapalli (K) village at Design Ch. 250+400 Km (total length 29.920 Km) under other Economic Corridor (NH(O)) programme on Hybrid Annuity Mode in the State of Telangana (Package-I). |
| Employer |
: National Highways Authority of India |
| Concessionaire |
: M/s Dineshchandra Kanakdurga Infra Private Limited |
| Independent Engineer |
: M/s AICONS Engineering Pvt. Ltd. in Joint Venture with Almondz Global Infra-Consultant Limited in association with KAIUS Consulting Pvt. Ltd. |
| Total Project Length |
: 29.920 Km |
| Contract value |
: Rs. 747.00 crores |
| Letter of Award Date |
: 29-Mar-2023 |
| Concession agreement signed |
: 17-August-2023 |
| Appointed Date |
: 15-Aug-2024 |
| Date of completion |
: 730 days from Appointed date (15.08.2024) |